Diary of a New Radio Control Model Flying Site by Tom
Laird & Jim McGlynn
![]() |
![]() |
|
| Aerial photos by Martin Gibbs, Forth Valley Soarers | ||
|
I recorded our experiences in building a new flying site in the hope that it may be of use to anyone else considering the same path. In
the beginning was the realisation that our (then) current flying site was not filling
all our needs. It was the wartime airfield at Kirknewton near Jim
McGlynn and I had spent a considerable amount
of time knocking on farmer's doors to no success and had all but given
up. |
||
|
However,
we placed an advert in the "Scottish Supermart"
and this resulted in an invitation to visit the farm in question. Following
a tour, one particular site was earmarked. It was 1/2 mile from the
nearest house, had a hard road up to a car park for a dozen cars, and
pilots would have the sun to their back when flying. Pretty
good? Not quite! The grass was 2 feet tall, and the whole place
was a peat bog on top of a clay sub-soil. That's a pretty bad combination. On
the upside, the farmer said he would cut and roll the grass, we could
fence off the area, and an Astro Turf, tarmac or concrete runway was not a problem. |
![]() |
|
|
Week 2 We
went back a week later with 3 other members to have another look. The
nice flat bit was running North/South but the approach would take a
plane too close to the village so that runway was out of the question.
The East / West was on a slope and that did
not look the best solution either. However, the slope would help the
ground drain a bit better so we went for it. Our reasoning was partly
that Woodsprings is also on boggy land and they have done it, so
why couldn't we? Week 3Sunday
morning. Went up with Jim for a couple of hours. Took
up a dozen bags of top-soil in case they're required. Took some
plastic sheeting and started hauling the grass to the end of the runway.
Dug out about 20 metres of the North / South
drain which was clogged up. That should help things. It's impressive how much can be accomplished in such a short
time. Week 4 Put
advert in "Scottish Supermart" for a petrol fly-mo. Buy it on the Wednesday
evening. Go up on the Sunday and cut half of the car park and the first
part of the runway, whilst Jim and John start digging a new East / West
drain along the side of the cut grass area. The place still looks better
in the dark. We need money and we need more helpers, but the place is
not really far enough on to impress people. It's getting dark at |
||
Week 5Phone
around for mini-digger prices, hard-core prices and field drain prices.
Jim phones the local council for road scrapings so we get put on their
backlog. Put advert in the "Scottish Supermart"
for field drain. Wednesday: They've got the ad in the wrong section so had to re-send it. Pick up some pallets on the way home. They need creosoating before they can be used. More money and another job to be done. |
![]() |
|
|
It
has rained pretty well all week. Went up on the Saturday for 4 hours
and cut another area of the car park, and another part of the runway.
The trick here is to cut it, rake it, then leave it for an hour to dry, then cut again. The ground
is pretty wet after the rain so no chance of getting the tractor and
a 4 & 1/2 ton roller on the case. Dug out another
10 metres of the new East/West runway drain. The peat
is very wet so it cuts easily. The water is now starting to flow so
perhaps we're making progress. Took time of to fly
the glider for 1/2 an hour. Lots of thermals
due to the standing water. Must get a noise
test done soon for the power people. Sunday. Should have picked up some Astro-turf. However, our contact has not been back
to us, and we don't have a lorry anyway. Wives stop play so we can't
do any work on the field. Spend some time repairing a crack in the fly-mo's skirt. Jim informs me that he has a contact for a motor
roller and that it can be delivered. How we get it across to the runway
is another matter since the ground is very wet in places. Week 6It
has rained solidly all week but surprisingly, the site is no wetter
than on previous visits. Wednesday:
We get two replies from the advert for field drain, but nothing has
come of them. Thursday:
Jim informs me that he has about a dozen 2 x 2 slabs for the pilot stance
area. Discuss using old engine oil on the pallets but reject as too
messy. Sunday
afternoon: Jim, John and I are joined by the SAA secretary, Harry West.
We finish clearing the main North / South drain, and cut two new drains
across the width of the runway. Water is flowing freely in all of them
so we are starting to see some result for our efforts. Need to dig at
least one more across the top and down the other side of the slope. We
do a noise test with my Mascot but it a fairly quiet engine (OS 40 LA)
so maybe it is not giving a true impression. Objectives
for next week: Must
get three aircraft up in the air.
Do the third cross runway drain and start on the other length-ways
one. I
took some photographs for the web site but they were pretty poor. Sunday
evening: The farmer phones me. He has 100 metres
of drain pipe. Also, he will dump some shale on the entrance, AND he
will cut more of the long grass. I ask him for some advertising blurb
about his farm for our web site. |
||
![]() |
![]() |
![]() |
Week 7Tuesday:
Visit the local garden centre. A 25kg bag
of grass seed, 50% rye is £100. Visit the greenkeepers
at the local golf course and get a contact name at Sports Turf Services
at Newbridge and call them for advice. They have a
seed that will cost about £40 for enough to do the area. If there is
a lot of moss we really need to hire a Scarifier
to cut through it. Also, it seems that coatings of sand will be benifical
as it will be absorbed into the peat, thereby breaking it up. Also it
will eventually get absorbed into the clay thereby acting as a route
for the water to flow through. We are now too late to sow grass seed
as the frost last night would have killed it. However, we may need to
put down some fertiliser over the winter.
The
salesman lives near the site so he will go have a look at the site.
He will call me middle of next week he says. Yeah, right! I'm still
waiting. It
rains all week. However, when I go up on the Sunday, it is no worse
than the week before. Unfortunately, rain stops play. All we get done
is to dig a new 10metre drain which was half full of water by the time
we left Week 8Monday:
Professor Spoor phones to discuss progress and drainage techniques.
Thursday:
Jim has found a mini-digger and driver for £50 a day. This
is the weekend of Jim's 40th birthday so there is absolutely
no chance of going up this Sunday. Okay!
I'm addicted. I went up on Sunday afternoon and dug another 15metres
of ditch. Week 9Jim
went up on Monday and finished the top drain. He also cleared about
10metres of the cut grass. Sunday. 4 people turn up AND the mini-digger which proceeded
to dig 60 metres of ditch before a hydraulic
leak stopped play. All the cut grass was cleared from the site, and
about 50metres of peat from the drains was removed. The site is now
starting to look a bit better. It's still wet, but that's not surprising
as we have had another week of serious rain. Week 10The
deep drain which the mini-digger had dug had filled with water on the
East side of the slope. This drain was taken further East
to meet up with an existing drain, and the water started to clear. This
amount of water must also have been cleared from the North side of the
slope rather than continue down onto the runway. Another lesson learned. 1"
of rain fell last night so the whole place was very wet. But so is every
other field in the county. The mini-digger could not put in our next
drain, so he joined our South drain to our East one, thereby completing
a trench all the way around the runway. Any water in the runway can
now only be rainfall. 3
visitors came up to the site and (surprise, surprise) a contractor to
quote for a tarmac runway. We
also have had an offer of a heavy duty petrol strimmer. I
gave the farmer a copy of the development plan which broke the site
down into bite-sized chunks, with proposals and estimates for each.
"No problem, very professional" he said.. Week 11You
guessed it! Another week of rain. Its now very
frosty at night, and there is no heat in the sun. When the frost melts,
the grass gets wet, and stays wet. The
Sunday was the day earmarked as the "Open Day" for potential
members. About 7 people including a Civil Engineer turned up. He examined
the site, and promised us a written report. We extended the main barrier
drain and allowed the water to drain off. A lot of the peat from the
cross-runway drains was removed, and by the end of the day, the place
was looking pretty tidy. We also got some flying done which was nice
for a change. The
development plan is now almost complete and is only awaiting the last
of the quotes. Next week is the SAA's A.G.M. so work will probably slow down until we hear
from the lottery / Awards for All application which we will be submitting. The
advert is almost ready, and the locations for the
posters has been agreed. Week 1225
copies of the advert have been made and these should get distributed
throughout the area over the next 2 weeks to libraries (note that you
should approach the central librarian and he/she will get the posters
distributed). The
first committee meeting has been set for the 10th Nov. Membership
currently stands at 10 but needs to be a lot higher. Spoke
with planning department and environmental health. Planning application
stuff has arrived so that needs looked at. Saw
some people looking at our advert on the noticeboard
at the SAA's A.G.M. so at least word will start to get around about
us. Spoke
to the Chairman of the Woodsprings Club. They have 10 feet of peat below them, and
a nice 100m x 10m tarmac runway. Total cost to date: about £50K. They
also do an airshow every year. Week 13 (oh-oh, unlucky for some) The
"Code of Practice for Model Aircraft Noise" has arrived. Basically
it's all just common sense. The
first committee meeting was held. Application forms for the local model
shop are required, and the New Members Welcome Pack will be put together
over the next couple of weeks. The
adverts are now being distributed. We
currently have one new person (Gordon's work colleague) showing an interest. The
bank account has now been opened. The
lottery application continued to be tweaked and has now gone for review
by our contact in West Lothian District Council. There are 2 versions
of the plan: one for a 3 year development and on for a 5 year development.
Sunday
was "meet-the-neighbours" day. We spoke to about 20 residents of the
local village and left letters with contact phone numbers. The response
in all cases was very positive. The other 26 will be done in due course. We also did a couple of test flights. Well, 1 test flight and 1 test crash. A clevis pin sheared and my Mascot spun in vertically from about 50 feet. Messy! The model was buried up to its wings in the peat. The prop wasn't even broken. Some minor damage was incurred when the front wheel sprung back when it hit the ground, and a minor bruise on the wing, but it's still intact. (The prop went straight in the bin anyway). |
||
| The "before & after" pictures of the path from the carpark to the runway. | ![]() |
![]() |
|
Week 14 & 15 (Xmas & New Year) Not
a lot has happened over these two weeks. The advert is now in the local
model shops. The advert is also in the local libraries and sports centres
in the area. Another
30 letters have been photo-copied to hand out to the neighbours
in the local village. We
have had some feedback on the lottery application. Basically we need
to make some changes to the constitution regarding the assets if the
club packs up, and we need to do more work on how we will try to bring
new people into the hobby. There
is now a sum of money earmarked as "Youth Development Fund"
shown on the budget for the next 3 years. We have the BMFA's
teacher guide and model price list, as well as hardcopies of the BMFA
handbook. Week 16The
major event this week was to get the lottery application approved and
sent off. This was done. A letter was sent out requesting informal planning
approval and press releases have been sent to 4 of the local newspapers.
We have had one new membership enquiry, with a further 1 nibbling at
the edge. We
also have a proper drawing / plan of the runway construction, courtesy
of the Civil Engineer who kindly visited a couple of weeks ago. We have
also found a squad who will lay the concrete properly for us. We
have a letter from the farmer saying that "we can use and develop
the site, and that barring any unforseen circumstances, we have the site for the next 5,
if not 10 years". The
17th Jan in the afternoon is the next scheduled visit to
the site. Lindsay Dickie, Don Imrie and Ian McLaren should also be there to give us their views on the
suitability of the site. I
now feel that we have turned a corner, and that things are starting
to come together. Its been a long and hard slog, with high levels of frustration
due to the rain, but very enjoyable nevertheless. We are learning a
lot, and hopefully others can learn from our experience. Week 17 A
press release was sent out to 4 of the local newspapers. One called
me and said the wanted to do a full blown article with photographs.
Consequently I sent them a copy of our "Welcome Pack" and
some supporting information about model flying in general. The photo-shoot
was arranged for the Saturday and it dawned bright and cold. About a
dozen people turned up with model including Martin Gibbs with a 4metre
Algebra, Ian McLaren with a £5000 7 foot Mirage
and Lindsay Dickie who gave a display (in
a 30MPH wind) with his OS70 powered AcroWot.
Following
the adverts for new members in the Scottish Supermart
we have received 4 calls from prospective members. Iain Weymss has donated a C.S.M.
R/C model flying simulator to the club. This is now available and anyone
with a PC can borrow it. The
"Welcome Pack" has now gone out to most members. |
||
| Errecting the electric fence in Year 2 (see later) | ![]() |
|
Week 18The
newspaper article turned out to be a double-page centre
spread in colour. It was pretty accurate with a little bit of reporters
licence thrown in for good measure. We received
5 phone calls, one person being the original Chairman in 1952, and represented
about 10 others. Another person represented about 6 others who were
having a hard time getting trained. Not bad if they all join up. All
adverts are now distributed, and all "Welcome Packs" have
been sent out. Busy week. The
council planner has been out to look at the site, and sees no problems.
Consequently, we will be making a formal planning application ASAP. The
current thinking is that we want all membership fees in by the 12th
Feb so that we know where we stand financially, with a committee meeting
on the 14th to draw up a detailed plan. We will hear from
the planning people on the 26th March and expect to start
work on the first week-end in April. The concrete will hopefully go
in at the beginning of May, depending on the weather. Currently
we have 12 members and 21 other "Welcome Packs" have been
sent out. I am now getting slightly concerned that the car park could
get quite crowded, and could become a limiting factor on how many members
we accept this year, or until we extend the car park. Our 5-year budget
shows 14 members this year, rising to 20 next year. The car park as
it stands can take about 12 cars, and parking on the roadside is not
an option. If only all problems were as nice to have as this one. Week 19Sunday
saw an early morning attack on the site with a strimmer.
Jim cut a path straight across from the car park to the runway. Those
reeds didn't stand a chance until the chord run out so we'll need to
get a new one and go back again. Dave Gillan
followed up with a 12 metre drain to let the standing water soak away. The drain
had an immediate effect and should result in a drier pathway to the
runway. We
also fully measured the site and posts were hammered in to mark out
the drive, car park, path and runway. Week 20The
tension mounts. Will our grant application be successful, or will we
need to do it the hard way? Will we have enough members to do it the
hard way? How many people are thinking they can just wait for the runway
to appear, and then join? Will the rain ever stop? And will the wind
ever fall below Gale Force? The
"Open Morning" was successful with 11 adults + 2 youths turning
up, plus 2 new phone calls in the evening. All "Welcome Packs"
have now gone so another dozen need photo-copying. The
Community Centre has been booked for the 28th Feb. The
land-fill contractor did not turn up - surprise, surprise. These guys
really are a pain - if the are not interested, why do they not just say so? Iain Wemyss has tracked down the
local councilor and we'll see if there is any other grant money available. The
runway construction plans have now arrived, and site plans are being
done for the planning application. Sunday:-
phoned an entry to the local newspaper regarding the club. I intend
using this to keep non e-mail people up to date with progress. Week 21The
big day arrived. We received a letter from the Scottish Sports Council
awarding us £4306 under the "Awards for All" scheme. Detailed
planning now needs to start asap. On
Sunday distributed the remaining letters to the neighbours.
Only 1 person voiced concern, but we still need to be careful. Spoke
to 2 possible contractors and arranged to get back in touch prior to
next site visit. One lives nearby so he's handy. Iain Wemyss has sourced a couple
of other grant applications so they need looking at. Another
new member has joined us. A good week for a change. Week 22 Not
a bad week when all is said and done. Plenty of sunshine
but very cold, and a lot of rain as well. All the local fields
still have lots of standing water so we are no worse than anyone else. The
main event this week was to send off the planning application. A last
minute action was to measure the distance from the runway to the road
which Jim managed to do somehow. The magic date is the 26th March when
we will hear from the planning committee. This in not really a concern
since the planners have already done a preliminary assessment and reckon
we will be okay. Nevertheless, you can't go spending £5000 on someone's
say-so. Detailed
planning is now underway so that we can start work at the beginning
of April. I
finally got around to adding buttons to the web site, and improving
the "No Frames" version. I've also got us linked from a few
other local sites. This is important - think about where the locals
will browse and get your club's web site linked from there. Week 23 & 24 There's
not a lot to report this week. We had to send more new maps to the planning
committee so we may not here until the 26th April. Major
disappointment. We
are in discussions regarding the indoor exhibition. Jim has a meeting
tomorrow to discuss but the overall idea is to do a 3-way presentation
between us, the Scottish Jet Team and the Scottish Aerobatics Team. I
have installed the R/C simulator training software on the local community
centre's computers for those non-computer
members. This turns out to be a GOOD IDEA.
|
||
| The North grass runway built in year 2, see later. | ![]() |
|
|
Week 25 We
have applied for and received £300 from the West Lothian Sports and
Recreation Association to buy a Real Flight simulator and a further
CSM one. Hopefully we will have these working at the exhibition. The
exhibition at Week 26 It's
been another hectic week. On Monday sent out 10 press releases regarding
the Jim
has had extensive discussions with the concrete squad. They are all
working 12 hour shifts, so we may have to do the whole job ourselves.
Now there's a surprise! Iain is trying to get concrete prices, and Started
making up the data sheets for the exhibition so that the public know
what they are looking at. These will be printed on card and will stand
beside each model. Scanned
a couple of pictures of the aerobatics team and uploaded them to the
web site. Think that we should really have a presentation page on one
of the web sites for each of the teams:- names, pictures, models, successes etc. On
Saturday morning I went over to Scoonie Hobbies
(60 mile round trip) to pick up the box of raffle prizes they donated
for Got
some nice photos & data from Martin Gibbs for the exhibition. Week
27
This was the BIG WEEK. The planning application was successful and the first indoor static model exhibition was held at the Freeport Shopping Complex. The exhibition was a success and we are on cloud nine. (and as usual there are plenty to choose from J) |
||
|
Week 28 The
big green button has been pushed and things lurch into operation. Sunday:
The HiMac is delivered to the site and parked away from prying
eyes. Make a final phone call to the contractor and speak with the driver.
All systems are go. At last! ( |
![]() |
|
|
We knew exactly where to look but they had sunk into
the mud hence the wasted hour. Very frustrating. By Tuesday: Rain
all day with some dry spells. Very cold wind.
07:40
Pick up the himac driver while Jim visits the demolition site to find
out when our rubble will arrive, only to discover that the rubble we
had been promised would not be forthcoming unless we could move it ourselves.
Jim arranges a tipper contractor. He also chases up the vibrating roller
hire company who had been told LAST WEEK that we needed the roller.
By the middle of the afternoon we gave up chasing. (How DO these companies
survive???) I
shoot off at Wednesday: ( ( (Jim
08:00) Meet lorry driver, load up the rubble and deliver to the site
( ( ( ( ( ( ( ( ( ( The
path from the car park to the runway is now covered with rubble and
is bedded in. ( (
|
||
| Picture showing the main runway just after the tarmac was laid. The leading edge was subsequently smoothed off. | ![]() |
|
|
Thursday ( ( This
was a very frustrating day. We could not get hold of the rubble provider
to find out what was going on. It was also a day of heavy rain, so the
open clay was getting broken up. Although we tried hard, 3 men alone
could not move 20 tons of type 1 quickly enough to protect it. Ian
Weymss did a great job in boarding up the
porta-wreck which has now been promoted to
Porta Cabin since it is now weatherproof,
has its door back on and is a nice shade of green thereby merging into
the background. Friday: Another
frustrating day! Colin was on-site at Colin
and I moved some of the rubble down to the gate entrance as this was
starting to get very soft and mushy, while Jim dug a drain from the
bottom of the runway to let the standing water clear. Colin
honed his D.I.Y. skills by painting the (now boarded up) windows. At
Saturday John
Donaldson arrived about Sunday John
again looked after the fort and supervised the unloading of 4 loads
of rubble. Things are now moving, although about a week behind schedule.
About |
||
|
Week 29 Meet
John Donaldson at the Teram suppliers at We
had arranged to meet one of the demolition contractors working in the
area, but as is now the norm, HE DID NOT SHOW UP!! A phone call found
out that he had been called to an emergency fire in Tuesday Back
to work for a rest. My real work that is. |
||
|
Week 30 - Week 34 This
was another exciting period. The local ice rink was being demolished
and after negotiations, we took delivery of about 800 tons of rubble.
The demolition company also put in a 32 ton Hi-Mac to spread the rubble.
In addition, a local cement works got in touch asking if we could use
their scrapped cement tiles. (Xmas has come early). We took delivery
of 20 pallets worth, wrapped in polythene and moved by fork lift to
the exact spot and arranged to take them for the forseable
future. |
![]() |
|
|
By
the end of all this we had a 50m x 20m car park, a 50m x 3m path to
the runway, and a 65m x 7m runway foundation complete with pilot stance
and starter box area. Special mention goes to Colin Hume who almost
lived on the site, co-ordinating deliveries
and keeping the main road clean and the neighbours
happy. All
we have to do now is clean up the site and lay
the tarmac. We're getting close now, and the end is in site. Week 35 Sunday
was earmarked for the tidy-up. The morning was nice and saw about 6
or 7 early risers getting stuck in. Unfortunately rain stopped play
about Week 36 We
received a bit of bad news. Our original planning permission was for
a concrete runway, but we submitted a request to change to tarmac. The
council wrote back saying "we would introduce an urban element
into a rural area". It’s a bog for goodness sake. Not only that,
but our planner had gone on holiday for 3 weeks. Negotiated
our rent payment as a brand new roll of Teram
instead of cash. That’s
more money in the runway fund. |
||
|
Week 38 Put
out a request for next year's fees to bolster the runway fund and got
an immediate donation of £100. "Ask and you might
be lucky and receive" is something we have learned. More tidy up work was carried out, and the long grass attacked with the strimmer. The sun cannot dry out the ground if the grass is too long and drains are our best friend on this site. Friday:
GREAT NEWS!!!! A letter arrived from the planners. They accepted our
points and gave permission for tarmac. All systems are now "go!" There is light at the end of the tunnel. Its all been worth it. All we need is another couple of hundred
pounds. Week 39This
was reasonably easy week. All I had to do was take a half-day off work
to meet the estimator from the local council to explain what we wanted.
Week
40
The quote arrives from the council and the go-ahead is given. |
||
Week 42Arrives
at site around The
runway should have been 6 metres wide. The
foundation was, because we checked it, but they only did the top surface
at 5 metres.
|
![]() |
|
Week 43 - 44Negotiated
100 tons of road bottoming as compensation for the narrow runway. Week 45Bottoming
material arrived. Farmers tractor was borrowed and all the bottoming material
was spread down either side of the runway, and at either end to give
good run-off areas. Week 46The
farmers quad bike and harrows was borrowed
and all the open clay was leveled off. We had the official opening day
looming so we really had to get the site tidied up. This just seemed
to take ages. Everytime you looked there was
something else needing done.
|
||
|
Year 2 Errected a 500m electric fence. Built
a grass runway adjacent to the tarmac one. (scraped out old top surface, put in drains,
put in new top soil, re-seeded). |
![]() |
|
|
Year 3 Foot
& Mouth stopped play for most of the year. Plans to surface the
access road and car park put on hold. |
||
| Year 4 Submitted a second planning application and applied for a second "Awards for All" award to allow us to install a safer car park, and a container to use as a club house. These are particularily useful for our older members who can get inside out of the cold. |
||
| Year 5 Submitted a third "Awards for All" award to bring the site up to competition level. The resulting work involved digging out a new pits area and re-filling with top soil, and importing, laying and leveling new top soil on the South runway. We also put in a cross wind runway. |
![]() |
|
![]() |
![]() |
|
Advice